Making cost estimates of construction works
Deciding on the initial data for cost estimation. The choice of the kind of cost estimate
1. Film in the standard version.
2. Film with subtitles.
3. Film with pauses. Listen and repeat.
4. Film with narration.
After listening to the above dialogue, mark the correct answer. Po wysłuchaniu powyższego dialogu zaznacz prawidłową odpowiedź.
Prawda | Fałsz | |
Investment cost estimate is drawn by the Contractor. | □ | □ |
The investor is responsible for drawing the investment cost estimate. | □ | □ |
Quantity survey works is calculated on the basis of technical documentation. | □ | □ |
BOQ is calculated on the basis of technical documentation. | □ | □ |
As-built BOQ is calculated on the basis of building stocktaking. | □ | □ |
BOQ is the estimation of the amount of already performed works. | □ | □ |
Quantity survey is the amount of work to be done. | □ | □ |
Initial data for cost estimation are determined by an Investor and a Contractor. | □ | □ |
Initial data for cost estimation are determined by an Investor and a Cost estimator. | □ | □ |
Cost estimate of construction works is the estimate of construction works connected with making a building structure. | □ | □ |
Match the Polish terms with their English equivalents. Połącz polskie terminy z ich angielskimi odpowiednikami.
drawings of a technical project, as-built bill of quantities, the bill of quantities (BOQ), equipment, technical project, quantity survey, building stocktaking, Investment cost estimate, initial data for cost estimation, Materials
Obmiar | |
Kosztorys inwestorski | |
Część rysunkowa projektu | |
Inwentaryzacja budowlana | |
Sprzęt | |
Projekt techniczny | |
Kosztorys powykonawczy | |
Dane wyjściowe do kosztorysowania | |
Materiały | |
Przedmiar |
Cost estimation of construction works
Match the appropriate equation with a proper name.Dobierz odpowiedni wzór lub symbol do danego określenia.
<span lang="en">net investment estimate value </span>, <span lang="en">cost of labour </span>, <span lang="en">direct costs </span>, <span lang="en">cost of equipment work </span>, <span lang="en">gross investment estimate value </span>, <span lang="en">cost of materials </span>
Match the Polish terms with their English equivalents. Połącz polskie terminy z ich angielskimi odpowiednikami.
cost estimation, direct costs, net investment estimate value, labour, cost of materials, gross investment estimate value, markup, quantity survey, Indirect costs, the bill of quantities (BOQ)
kosztorysowanie | |
obmiar | |
przedmiar | |
robocizna | |
koszty pośrednie | |
koszty bezpośrednie | |
wartość kosztorysowa brutto | |
wartość materiałów | |
wartość kosztorysowa netto | |
narzuty |
Drawing up a cost estimate
After watching the films and listening to the comments of the reader, mark the correct answer. Po obejrzeniu filmów i wysłuchaniu komentarza lektora zaznacz prawidłową odpowiedź.
Prawda | Fałsz | |
Rate items organised by theme constitute chapters. | □ | □ |
The value of indirect costs is always constant. | □ | □ |
Rate item includes the numbe, base, description of works, quantity survey/the bill of quantities (BOQ) and labour outlay, materials and equipment work. | □ | □ |
NCE is National Contractors Estimator . | □ | □ |
The title page contains a table of values of integrated elements. | □ | □ |
Standard inputs are the amount of labour, materials and equipment work per unit of a given work. | □ | □ |
Markup is the amount of labour, materials and equipment work per specific quantity of construction works. | □ | □ |
Table of values of integrated elements is the summary of cost estimate. | □ | □ |
Markup for cost estimate and National Contractors Estimator
Grammar
Glossary
/əz bɪlt bɪl əv kwɒn.tə.tiz/ [noun, countable] kosztorys powykonawczy
/bɪl əv kwɒn.tə.tiz/ /bi əʊ kjuː/ [noun, countable] przedmiar robót
/ˈbɪl.dɪŋ ˈstɒkˌteɪ.kɪŋ/ [noun, uncountable] inwentaryzacja budowlana
/kənˈtræk.tər/ [noun, countable] wykonawca
/kɒstˈes.tɪ.meɪt/ [noun, countable] kosztorys
/kɒstˈestɪmeɪtər/ [noun, countable] kosztorysant
/kɒsts əv məˈtɪə.ri.əlz/ [noun, countable, plural] koszty zakupu materiałów
/daɪˈrekt kɒsts/ [noun, countable,plural] koszty bezpośrednie
/ˌdɒk.jə.menˈteɪ.ʃən/ [noun, uncountable] dokumentacja
/ɪˈkwɪp.mənt/ [noun, uncountable] sprzęt
/ɡrəʊs ɪnˈvest.mənt ˈes.tɪ.meɪt ˈvæl.juː/ [noun, uncountable] wartość kosztorysowa brutto
/ˌɪn.daɪˈrekt kɒsts/ [noun, countable,plural] koszty pośrednie
/ɪnˈvest.mənt kɒstˈes.tɪ.meɪt/ [noun, countable] kosztorys inwestorski
/ɪnˈves.tər/ [noun, countable] inwestor
/ˈleɪ.bər/ [noun, uncountable] robocizna
/ˈleɪ.bə kɒst/ [noun, countable] stawka robocizny
/məˈʃiːn aʊər/ [noun, countable] maszynogodzina
/mæn aʊər/ [noun, countable] roboczogodzina
/məˈtɪə.ri.əlz/ [noun, countable,plural] materiały
/ˈnæʃ.ən.əl kənˈtræk.təz ˈestɪmeɪtər/ [noun, countable] katalog nakładów rzeczowych
/ net ɪnˈvest.mənt ˈes.tɪ.meɪt/ [noun, uncountable] wartość kosztorysowa netto
/ˈɒf.ər kɒstˈes.tɪ.meɪt/ [noun, countable] kosztorys ofertowy
/ˈaʊt.leɪ/ [noun, countable] nakłady
/ˈəʊ.və.hedz/ [noun, countable,plural] narzut
/praɪs lɪst/ [noun, countable] cennik
/ˈprɒf.ɪt/ [noun, countable or uncountable] zysk
/ˈpʌb.lɪk wɜːks ˈkɒn.trækt/ [noun, countable, singular] zamówienia publiczne
/ˈkwɒn.tə.ti ˈsɜː.veɪ/ [noun, countable] obmiar
/reɪt ˈaɪ.təm/ [noun, countable] pozycja kosztorysowa
/rəʊd ənd striːt ˈsɜː.fɪsiz/ [noun, countable, plural] nawierzchnie na drogach i ulicach
/ˈstæn.dəd ˈɪn.pʊts/ [noun, countable, plural] norma nakładów
/ˌsʌp.lɪˈmen.tər.i ˈes.tɪ.meɪt/ [noun, countable] kosztorys dodatkowy
/ˈtek.nɪ.kəl ˈprɒdʒ.ekt/ [noun, countable] projekt techniczny
/ˈjuː.nɪt kɒst/ [noun, uncountable] koszt jednostkowy
/ˈjuː.nɪt praɪs/ [noun, countable] cena jednostkowa
/ˌviː.eɪˈtiː/ [noun, uncountable] podatek vat